projects

Jumboising Queen of the NetherlandsTrailing Suction Hopper Dredger (TSHD)

Image of Jumboising Queen of the Netherlands

One of the most powerful dredgers

Jumboising Queen of the NetherlandsTrailing Suction Hopper Dredger (TSHD)

One of the most powerful dredgers

Queen of the Netherlands is a Dutch Trailing suction hopper dredger ship constructed in 1998. After lengthening in 2009, she was the largest and most powerful dredger in the world. Vuyk Engineering Rotterdam carried out a major part of the total engineering package required for the fabrication works in Thailand.

Customer request Concept design Basic design

The Dutch dredging contractor Royal Boskalis Westminster N.V.asked Vuyk to make extensive modifications to The Queen of The Netherlands’ design. This resulted in an enlargement of the dredger’s hopper capacity with more than 50 percent and improved deep-water dredging capabilities.

Specifications

Launched in
1999
Length
230.00 m
Breadth
32.00 m
Depth
15.90 m
Draught
13.70 m
Capacity
35000 m
Speed
16.00 m
Dredging depth
83 m
Two trailing suction pipes, diameter
1,200 mm
Total installed power
28,000 kW
Dredge pump output
SB: 7,000 kW, PS: 6,000 kW

Customer request

Concept design

  • Preliminary design package
  • Preliminary tender information for inquiries

Basic design

  • Design package key components
  • Final tender information for (yard) inquiries

The vessel, originally built by Verolme Shipyard Heusden, belongs to the world’s largest trailing suction dredgers after lengthening. In 1999, the Dutch dredging contractor Royal Boskalis Westminster N.V. took delivery of the upgraded trailing suction hopper dredger ’Queen of The Netherlands’. In close cooperation with the owners, Vuyk Engineering Rotterdam carried out a major part of the total engineering package required for the fabrication works in Thailand. The actual lengthening was executed in a dry-dock in Singapore. The enormous ship has the equipment to dredge almost any material; such as clay, silt, sand and rock.

The new section was prefabricated and fully equipped with bottom doors, hydraulic cylinders and piping in Thailand. On completion, the section was towed to a shipyard in Singapore. Before the arrival of the Queen, all prefabrication and preparations were finalized. The vessel was then brought into a dry dock and was cut into two pieces. Next the fore ship was floated out and the aft ship remained in the dry-dock. Then the new section and the fore ship were floated back sequentially. After the dock was dry again and dock blocks were settled, both sections were skidded to the right position, aligned and welded to the aft ship. In the meantime deck sections, other steel sections and additional equipment were fitted. The vessel was put back into service after a series of extensive tests.
 

Location

Need to get in touch with the team?

We are all ears
VUYK engineering